The following work was completed Sat May 3rd.
Picture to the right is Don, Landon, Darren, Timber, Caleb, Conrad, Jacob, Steve, Guy and Christopher. Not pictured are Ginny, Alicia.

1. Fence at east side of main pen was stablized by installing 3 posts in concrete along side.
2. Water tank at big mill was cleaned out
3. Tin roofs were repaired on ranch house and branding station.
4. The two northern fences that created 2 holding pens in the lane from the Double Knoll pasture to the ranch house were removed.
5. A lot of useless wire and wood was cleaned up from the area south of the wind mill on the east side of the hill.